Available in Sage 50 Quantum Accounting.
            Enter a Revision
            How Do I...
            
            Follow the steps below to make changes to components 
 in the bill of materials. When you make changes to the bill of materials 
 for an assembly item that has been used in a transaction, you either enter 
 a new or edit an existing revision.
            
                - From the Maintain 
 menu, select          Inventory Items. 
 The Maintain Inventory Items window appears.
- Select the Item 
 ID of the assembly item that you want to enter a revision for, 
 then select the          Bill of Materials 
 tab.
- Select the Revisions 
 button. The button is located at the bottom of the tab on the right side. 
 The          Revisions window appears.
- To 
 create a new revision, select the          New 
 button from the toolbar. 
To edit an existing revision, 
 first select a revision in the list to edit, then select the          Edit 
 button from the toolbar. 
                Depending upon your selection, either the Create 
 a New Revision or the          Edit an 
 Existing Revision window appears.
                - Select the Effective 
 Date for this revision. The effective date is very important because 
 it determines when this revision will be used by Sage 50 to build assemblies.
- Make the necessary changes to the bill of materials. 
 You can use the buttons in the window to Add, Remove, Move Up, Move Down, 
 Reset All, or Clear All items in the bill of materials. 
- In the Note 
 field, type information that will help you identify why the revision was 
 made. This note will appear in the Revisions window along with all of 
 the other revisions that have been made for this item. If a note is not 
 entered, Sage 50 will automatically enter a generic note listing the 
 date, time, and user who entered the revision.
- When you have finished making changes to bill 
 of materials, select the Save 
 button to save this revision.
                Note: If you save 
 a revision that precedes the currently active revision, saving may take 
 several minutes. For example, let's say you have an assembly created on 
 January 1, 2016 and an assembly created on March 1, 2016.  If 
 you now add a revision dated February 1, 2016, the assembly created on 
 March 1, 2016 must be unbuilt and then rebuilt with the revision dated 
 February 1, 2016. Updating the records may take several minutes. A message 
 will appear to indicate that the records are being updated.
             
            What do you want to do next?